Retrospective
What did we do well?
- Project Admin w/ JIRAUser Managment Software (Atlassian) (manipulations on sub-tasks, stories, sprints, etc), but arguably such actions shouldn't have been required had sprint planning and execution have been better.
- Capturing/tracking effort & work on the project.
- Process discipline
What should we have done better?
- Capacity planning continues to be a problem. The sprint & associated stories should NOT have to be modded after-the-fact
- Should have recognized the existence of an Epic ("information displays") prior to inclusion in the Sprint.
What will we do differently next time to improve?
deliberately pull in fewer story points than believed possible. The Capacity Planning problems which require stuff to get thrown back into the backlog are crap and need to stop.